Regulation of an old Land Use Plan, preserved as a historical source.
Summary of the regulations:
Title 1 General Provisions
Title 2 Provisions applicable to urban areas
Title 3 Provisions applicable to natural areas
DEPARTMENT OF CALVADOS
VIERVILLE SUR MER
LAND USE PLAN
2 RULES
AMENDMENT No. 2
Approval
Initial POS, Approved on September 27, 1979
1ère MODIFICATION, Approved on August 29, 1986
1ère REVISION, Approved April 24, 1995
Seen to be annexed to the deliberation of the municipal council dated March 30, 2001
POSMYOUCK Design Office - Urbanist S.F.U. - D.E.S.S. Planning
The doors of Dover - 14440 DOUVRES-LA-DELIVRANDE - Tel: 02.31.37.72.22 - Fax: 02.31.37.71.64.
_______________________________________________
TITLE IGENERAL PROVISIONS
This regulation is established in accordance with Article R 123-21 of the Urban Planning Code.
The main articles of the Urban Planning Code cited in this regulation are reproduced in the documentary annex.
ARTICLE 1. TERRITORIAL SCOPE OF THE PLAN
This regulation applies to the entire territory of the Commune of VIERVILLESUR-MER.
ARTICLE 2. RESPECTIVE SCOPE OF THE REGULATION WITH REGARD TO OTHER SPECIFIC LEGISLATION RELATING TO A LAND OCCUPATION
REMINDERS:
* The construction of fences is subject to authorization;
* Various installations and works are subject to the authorization provided for in Articles R 442-1 et seq. of the Urban Planning Code;
* Demolitions are subject to the demolition permit in the cases referred to in Article L 430-1 of the Urban Planning Code;
* Tree cutting and felling are subject to authorization in classified wooded areas and for classified hedges listed on the plan;
* De-easing is subject to authorization in unclassified wooded areas. On the other hand, requests for clearings are inadmissible in the classified wooded areas on the map.
___________________
The provisions of this regulation replace those of Articles R 111-1 to R 111-24 of the Urban Planning Code with the exception of those of Articles R 111-2, R 111-3-2, R 111-4, R 111-14-2, R 111-15 and R 111-21 which remain applicable.
R 111-2
The building permit may be refused or granted only subject to compliance with the special requirements if the constructions, by their location or dimensions, are likely to affect public health or safety.
The same applies if the projected constructions, by their location near other facilities, their characteristics or their location, are likely to harm health or public safety.
R 111-3-2
The building permit may be refused or granted only subject to the observant of special prescriptions if the constructions are likely, by their location, to compromise the conservation or development of an archaeological site or remains.
R 111-4
The building permit may be refused on land that is not served by public or private roads under conditions that meet the importance or destination of the building or set of buildings envisaged, and in particular if the characteristics of these roads make it difficult to circulate or use firefighting equipment.
It may also be refused if accesses pose a risk to the safety of public road users or to that of people using these accesses. This safety must be assessed taking into account, in particular, the position of the accesses, their configuration and the nature and intensity of the traffic.
The issuance of the building permit may be subject to
a) To the construction of installations suitable for ensuring the parking outside of public roads of vehicles corresponding to the needs of the building to be built;
b) To the construction of private roads or any other special facilities necessary to comply with the safety conditions mentioned in second paragraph above.
The construction of more than one parking area per dwelling cannot be required during the construction of rental housing financed with a state-supported loan.
The obligation to build parking areas is not applicable to transformation or improvement work on buildings allocated to rental housing financed with a State-supported loan, including in the case where this work is accompanied by the creation of net non-work surface, up to a ceiling of 50% of the net off-work area existing before the start of the work.
The number of accesses to public roads may be limited in the interest of safety. In particular when the land is served by several lanes, constructions may only be authorized provided that access is established on the road where the inconvenience to traffic will be the least.
R 111-14-2
The building permit is issued in compliance with the environmental concerns defined in Article 1 of Law No. 76-628 of July 10, 1976 on the protection of nature. It may only be granted subject to the observant of special requirements, if the constructions, by their location, their destination or their dimensions, are likely to have harmful consequences for the environment.
R 111-15
The building permit may be refused or granted only subject to the observance of special requirements when, by their importance, location, and use of constructions would thwart the land use and urban planning action as it results from the provisions of the master plans concerning new agglomerations approved before 1er October 1983 or, after that date, under the conditions provided for in b of Article of Article 122-22.
R 111-21
The building permit may be refused or granted only subject to the observances of special prescriptions if the constructions, by their location, their architecture, their dimensions, or the exterior appearance of the buildings or works to be built or to modify are likely to harm the character or interest of the surrounding places, sites, natural or urban landscapes, as well as the preservation of monumental perspectives.
Also applicable are, notwithstanding the provisions of this regulation, the provisions of Article R 315-28, 3rd paragraph, which specifies that:
"In all cases, the authorization to allotment may be refused or granted only subject to the observance of special requirements, on the basis of the provisions mentioned in Article R 111-1, when, in particular by the situation, shape or size of the lots, the operation is likely to harm the character or interest of neighboring places, natural or urban sites or landscapes".
Also remain applicable to the municipal territory, notwithstanding the provisions of the Land Use Plan:
• Articles L 111-9 and L 421-4 relating to the perimeters of declaration of public utility;
• Article L 111-10 relating to public works perimeters.
The requirements under the specific legislation concerning public utility easements (the list of these easements and their content are annexed in the file of the Land Use Plan) also constitute higher standards to which the provisions of the Land Use Plan are subject.
Are and remain applicable to the municipal territory:
• Articles of the Urban Planning Code or other legislation concerning:
• Sensitive natural areas,
• The right of urban pre-emption,
• Deferred development areas.
• The law of September 27, 1941 regulating archaeological excavations and in particular Article 14 concerning fortuitous discoveries:
-
- Article 14
"Any fortuitous movable or immovable discovery of Prehistory, History, Art, Archaeology and Numismatics, must be reported immediately to the Regional Directorate of Cultural Affairs of Lower Normandy (Regional Archaeology Service, 13 bis rue Saint-Ouen, 14 052 CAEN CedexO4), either through the City Hall or the Prefecture of the Department. The remains discovered must under no circumstances be alienated or destroyed before examination by a specialist mandated by the Regional Conservatory. "
Any offender will be liable to the penalties provided for in Article 322.2 of the New Criminal Code.
-
- Article 15
If the continuation of research presents a public interest from the point of view of prehistory, history, art or archaeology, the excavations may only be continued by the State or after authorization of the State, under the conditions provided for in Chapters 1 and II of this decree.
Provisionally, the Minister of Cultural Affairs may order the suspension of research for a period of six months from the day of notification.
During this time, the land where the discoveries were made are considered classified and all the effects of the classification are applicable to them.
ARTICLE 3 DIVISION OF THE LAND INTO ZONES
The territory covered by the Land Use Plan (P.O.S.) is divided into urban areas (areas equipped or under equipment) and natural areas (less or not equipped areas).
URBAN AREAS are designated by the reference index U (zone UC, UD, ...)
NATURAL ZONES are designated by the reference index N (Zones 1NA, NB, NC, ND,... )
The plan also indicates:
• CLASS LAND AS WOODED SPACES to be preserved, protected, or created to which the provisions of Articles R 130-1 to R 130-15 of the Urban Planning Code apply.
• RESERVED LOCATIONS to public roads and works, general interest installations and green spaces to which the provisions of Articles L 123-1, 6e and 8e, L 123-9, R 123-18 II, 2° and 3°, R123-22,2°, R 123-24, 1er and R123-32 of the Urban Code apply.
ARTICLE 4 MINOR ADAPTATIONS
1) The provisions of Articles 3 to 13 of the regulations of each zone may be subject to minor adaptations, only in the case where such adaptations are made necessary by the nature of the soil, the configuration of the parcels or the nature of the neighbouring constructions. The department responsible for examining the application shall examine, if necessary ex officio, those adaptations which are authorized by the competent authority to rule.
2) When an existing built-in building does not comply with the rules laid down by the regulation applicable to the area, the building permit may only be granted for work that is intended to improve the conformity of these buildings with the said rules or that has no effect on them.
TITLE He
PROVISIONS APPLICABLE TO URBAN AREAS
CHARACTER OF THE AREA
This equipped urban area is mainly used for housing in the form of individual constructions or small low-density sets.
Activities that are the natural complement of the habitat are not excluded. However, the dominant part of the dwelling must give it a residential area character.
ARTICLE UC1 - TYPES OF LAND OCCUPATION OR USE
AUTHORIZE
-
- Constructions or installations of any destination whatsoever, subject to the prohibitions mentioned in Article UC2;
-
- Subdivisions with main residential use;
-
- Facilities classified for the protection of the environment which, by their destination, are linked to housing and urban activity and provided that they do not cause nuisance incompatible with them;
-
- Public or general interest facilities;
-
- Excavations and grounding related to infrastructure equipment and public or general interest equipment.
ARTICLE UC2 - PROHIBITED TYPES OF LAND OCCUPATION OR USE
-
- Constructions for industrial, commercial or agricultural warehouse use;
-
- Subdivisions for the use of activities
-
- Facilities classified for environmental protection other than those mentioned in Article UC1;
-
- Quarries, excavations and land-raising except those related to infrastructure equipment;
-
- Makeshift shelters, scrap metal, demolition materials, waste and disused vehicles;
-
- Light leisure accommodation (camping, caravans, PRL)
-
- The parking of caravans for a duration of more than 3 consecutive months per year or not.
ARTICLE UC3 - ACCESS AND ROADS.
Accesses and roads created must meet the conditions set out in Article 2 of Title 1 of this Safety Regulation (Article R 111.4 of the Urban Planning Code).
Regardless of the size of the subdivision or housing group, it will be required, in a non-private space, the possibility of subsequent road connection with any adjoining operations.
ARTICLE UC4 - NETWORKS.
Water:
Connection to the drinking water network is mandatory for any new construction or installation requiring a water supply. Constructions that cannot be served by water are not allowed.
Sanitation:
Wastewater:
Connection to the sanitation network is mandatory for any new construction.
In the absence of a network, the autonomous sanitation of buildings in accordance with the departmental health regulations is authorized. The facilities will have to be planned to be easily connectable to the public network when it is built.
Rainwater:
When the evacuation network exists, the improvements made on any land must be such that they guarantee the flow of rainwater into the collection network.
In the absence of a network, the builder will have to carry out at his expense the improvements allowing the free flow of rainwater. In addition, the manufacturer will carry out on its land and at its expense, appropriate and proportionate devices allowing direct evacuation and without stagnation.
ARTICLE UC5 - LAND CHARACTERISTICS
To be buildable, new plots created by subdivision or division must not have an area of less than:
- 500 m2 when served by a collective sanitation network
- 1000 m2 when they cannot be served by a collective sanitation network.
These provisions do not apply to infrastructure or general interest equipment.
ARTICLE UC6 - IMPLANTATION OF CONSTRUCTIONS IN RELATION TO THE TRACKS
Any new construction must be implemented with a minimum retreat of 5 meters from the alignment of the tracks.
In the event of de facto alignment of the island or the street in question, the installation of the constructions with the existing alignment or defined by an alignment plan is authorized.
Different setbacks may be authorized compared to the new lanes created on the occasion of subdivisions and housing groups or in the event of extension of existing buildings, provided that they do not harm the proper functioning of traffic.
Technical works necessary for the operation of public or general services are not subject to the distance and setback rules.
ARTICLE UC7 - IMPLEMENTATION OF CONSTRUCTIONS IN RELATION TO SEPARATIVE LIMITS
The distance counted horizontally from any point of a building to the point closest to the separating limit must be at least equal to half of the difference in altitude between these two points, without being able to be less than 4 meters. This minimum is reduced to 2 meters in the case of old plots less than 500 m2.
However, the separative limits are authorized:
-
- Constructions with a total height of less than 3 meters. this height can be increased to 5 meters at the ridge and 3 meters at the sewer when the wall installed at the separating limit is a gable wall.
- in order to ensure the harmony of the facades, constructions backed by existing buildings of greater height within the height limits defined in Article UC10.
Different setbacks may be authorized in the event of an extension of existing buildings.
These provisions are not applicable to the new separate boundaries created on the occasion of subdivisions and housing groups.
Technical works necessary for the operation of public or general services are not subject to the distance and setback rules.
ARTICLE UC8 - IMPLEMENTATION OF CONSTRUCTIONS IN RELATION TO EACH OTHER ON THE SAME PROPERTY.
Two non-contiguous constructions located on the same property must be at a distance from each other at least equal to the height (sewer) of the highest of the two buildings, and never less than 4 meters. This distance can be reduced without being able to be less than 2 meters when the face-to-face parts do not have main bays. It is specified that kitchen berries are assimilated for the application of this article, to main berries.
ARTICLE UC9 - GROUND CLEARING OF BUILDINGS
The ground clearance of the buildings must not exceed 35% of the total area of the plot.
ARTICLE UC10 - HEIGHT OF CONSTRUCTIONS
The maximum number of building levels is set at 3, including convertible or non-buildable attics, but not including the basement(s).
The upper level of the ground floor may not exceed the highest level of the natural land, on the right-of-way of the construction, by more than 0.60 m.
Infrastructure equipment is exempt from the rule of heights when their technical characteristics so require.
ARTICLE UC11 - EXTERIOR APPEARANCE
Constructions of any kind must not harm, by their external appearance, the character or interest of neighboring places, sites, natural or urban landscapes.
All traditional architecture foreign to the region is prohibited as well as any traditional architecture pastiche
The fittings or extensions of existing buildings must respect the character of the initial building with regard to the harmony of volumes, the scale of the drilling and the associations of materials and colors.
-
- MATERIALS
Constructions must be made of materials whose shade is as close as possible to the traditional materials used in the region.
A) Facades
Facade walls that are not made of materials intended to remain apparent, such as cut stone, apparatused rubble, slate essentage, solid grouted brick, slate ensentage, must receive a facing or plaster, either dyed in the mass, or painted. The plasters or paints must be of a light tone, harmonizing with the tone of the Caen stone. Any painting, or colored element, distinct from the general tone of the construction, must be motivated by the arrangement of the volumes or architectural elements. The use of white color on exterior walls is prohibited.
Are prohibited:
• the bare use, in facing, of materials manufactured to be covered with a coating or coating, such as plaster tile, hollow brick. However, exposed concrete can be authorized if it is made with apparatus formwork and cast with care in order to remain raw.
• Imitations of materials such as false brick, false panels of wood.
B) Blankets
Constructions with a simm will be covered with slate or natural or aged flat tile.
Are admitted: I~
• materials with a similar appearance (slate, stained fiber, etc....)
• the large mold mechanical tile (22 m2) with a flat pure brown tone.
Are prohibited for constructions for residential use:
• the square model slate placed diagonally.
•The large mold mechanical tile models with dimensions, diamonds or similar patterns.
• corrugated fiber cement plates.
• unconcealed metallic materials (galvanized sheet metal).
For the annexes to the house, the same building materials must be used as for the main building.
- FORMS AND VOLUMES :
Regardless of the size of the volume of the construction, elongated proportions are recommended.
a) roofs of buildings for use d'habitation
Symmetrical gables roofs with a slope of 40° to 60° are
Mandatory. Terraced roofs are prohibited.
However, roofs with a single low slope are allowed for constructions for annex use located in a separate limit.
Gaya wings or "Norman croups" are prohibited.
Any roof overhangs will be limited to 15 cm.
The skylights, if they are not included in the roof plan, will be straight and implanted in the lower part of the slope and of vertical and narrow shape.
These provisions do not apply in the case of repair of the roofs of existing buildings.
Different characteristics may be authorized for existing constructions in the case of the extension or connection of the existing roof to the projected extension.
-
- FENCES:
They must consist of hedges or any other clear-track device.
Solid fences meeting the same provisions as facade walls (see "materials") are authorized over a maximum height of 1.80 meters provided that they do not cause any inconvenience to visibility along public roads.
Are prohibited: molded and prefabricated elements on the edge of the tracks or visible from them.
-
- Various
The construction of annexes such as huts, chicken coops, shelters, etc.. made with makeshift means are prohibited.
Verandas and greenhouses are not subject to the provisions of this article, to with the exception of those relating to general aesthetics.
ARTICLE UC12 - PARKING
The parking of vehicles corresponding to the needs of the constructions must be ensured off public roads
ARTICLE UC13 - PLANTATIONS
Existing plantations will be maintained or replaced by equivalent plantations.
For subdivisions and housing groups, a common space must be developed with a minimum area obtained equal to 10% (not including roads) of that of the land.
50% of the area of the plots will be treated in planted green spaces and will include at least one tall tree per 300 m2 of land.
Wooded areas classified on the plan to be preserved or created will be protected and subject to the regime of Articles R 130.1 to R 130.15 of the Urban Planning Code.
ARTICLE UC14 - LAND USE COEFFICIENT (C.O.S.)
The Land Use Coefficient (C.O.S.) defined in Article R 123-22 of the Urban Planning Code is set at 0.30.
For subdivisions and housing groups, the COS applicable to each lot must be fixed by the special regulation so that on average the previous standard on the set in question is not exceeded.
The C.O.S. does not apply to the construction of public or general interest equipment.
ARTICLE UC15 - EXCEEDING THE LAND USE COEFFICIENT
Exceeding the C.O.S. is allowed:
• when its application to a plot does not allow a minimum area of 180 m2 to be stated. Overtaking in this case is possible until this surface is obtained. It is then accompanied by the payment of the participation provided for in Article L 332.1 of the Urban Planning Code,
• for identical reconstruction after a disaster.
UD ZONE
CHARACTER OF THE AREA
This urban area is mainly assigned to urbanization and activities (shops, services, etc.) which are its natural complement.
The implantation rules must give this area a relatively airy character.
Two sub-sectors (UD and UDa) are defined according to the parcel minima selected.
ARTICLE UD1 - TYPES OF OCCUPATION OR LAND USE AUTHORIZED.
• constructions or installations of any destinations, subject to the prohibitions mentioned in Article UD2;
• facilities classified for environmental protection subject to declaration which, by their destination, are linked to housing and urban activity and provided that they do not cause nuisance incompatible with them;
• public or general interest facilities
• excavations and grounding related to infrastructure equipment and public or general interest equipment.
ARTICLE UD2 - TYPES OF LAND OCCUPATION OR LAND USE PROHIBITED
-
- Facilities classified for the protection of the environment, except those mentioned in Article UD1;
-
- Industrial, commercial and agricultural warehouse constructions;
-
- Subdivisions for the use of activities
-
- Quarries, excavations and soil raisings except those mentioned in Article UD1;
-
- Makeshift shelters, scrap metal deposits, demolition materials, waste and disused vehicles;
-
- Light leisure accommodation (camping, caravannage, PRL),
-
- Caravan parking regardless of the duration.
ARTICLE UD3 - ACCESS AND ROADS.
Accesses and roads created must meet the conditions set out in Article 2 of Title 1 of this Safety Regulation (Article R 111.4 of the Urban Planning Code).
ARTICLE UD4 - NETWORKS.
Water:
Connection to the drinking water network is mandatory for any new construction or installation requiring a water supply. Constructions that cannot be served by water are not allowed.
Sanitation:
a) Wastewater:
Connection to the sanitation network is mandatory for any new construction.
In the absence of a network, the autonomous sanitation of buildings in accordance with the departmental health regulations is authorized. The facilities will have to be planned to be easily connectable to the public network when it is built.
b) Rainwater:
When the evacuation network exists, the developments made on any land must be such that they guarantee the flow of rainwater into the collection network.
In the absence of a network, the builder will have to carry out at his expense the improvements allowing the free flow of rainwater. In addition, the manufacturer will carry out on its land and at its expense, appropriate and proportionate devices allowing direct evacuation and without stagnation.
ARTICLE UD5 - LAND CHARACTERISTICS
To be buildable, new plots created by subdivision or division must have an area greater than:
-
- 1000 m2 in the UDa sector
-
- 2000 m2 in UD sector
This provision does not apply to public or general interest equipment and buildings. It also does not apply, in the UDa sector, to old parcels served by the collective sanitation network.
ARTICLE UD6 - IMPLANTATION OF CONSTRUCTIONS IN RELATION TO THE TRACKS
Any new construction must be implemented with a minimum withdrawal of:
-
- 30 meters by the axis of the RD 514
- 5 meters from the alignment of the other tracks.
In the event of de facto alignment of the island or the street in question, the installation of the constructions with the existing alignment or defined by an alignment plan is authorized.
Different setbacks may be authorized compared to the new roads created on the occasion of subdivisions and housing groups in the event of an extension of existing buildings, provided that there is no inconvenience to safety.
Technical works necessary for the operation of public or general interest services are not subject to distance and setback rules.
ARTICLE UD 7 - IMPLEMENTATION OF CONSTRUCTIONS IN RELATION TO SEPARATIVE LIMITS
The distance counted horizontally from any point of a building to the point closest to the separating limit must be at least equal to:
In the UD sector
Half of the difference in altitude between these 2 points, without being able to be less than 4 meters.
In the UDa sector
Half of the difference in altitude between these 2 points decreased by 4 meters without being able to be less than 2 m.
In the entire UD sector, however, are authorized, in separate limits:
-
- Constructions with a total height of less than 3 meters. This height can be increased to 5 meters at the ridge and 3 meters at the sewer when the wall installed in the separating limit is a gable wall.
- in order to ensure the harmony of the facades, constructions facing existing buildings of greater height within the height limits defined in Article UD10.
Different setbacks may be allowed in the event of an extension of existing buildings.
These provisions are not applicable to the new separate boundaries created on the occasion of subdivisions and housing groups.
Technical works necessary for the operation of public or general services are not subject to the distance and setback rules.
ARTICLE UD8 - IMPLANTATION OF CONSTRUCTIONS IN RELATION TO EACH OTHER ON THE SAME PROPERTY.
Two non-contiguous constructions located on the same property must be at a distance from each other at least equal to the height (sewer) of the highest of the two constructions and never less than 5 meters.
This distance can be reduced without being able to be less than 3 meters when the opposite parts of facades do not have main bays. It is specified that kitchen berries are assimilated for the application of this article, to main berries.
ARTICLE UD9 - GROUND CLEARING OF CONSTRUCTION
The ground clearance of the buildings must not exceed 25% of the total area of the plot.
ARTICLE UD10 - HEIGHT OF CONSTRUCTIONS
The maximum number of building levels is set at 3, including convertible or non-buildable attics, but not including the basement(s).
The upper level of the ground floor may not exceed the highest level of the natural land, on the right-of-way of the building, by more than 0.60 m.
Infrastructure equipment is exempt from the height rule when its technical characteristics so require.
ARTICLE UD11 - EXTERIOR APPEARANCE
Constructions of any kind must not harm, by their external appearance, the character or interest of neighboring places, sites, natural or urban landscapes.
All traditional architecture foreign to the region is prohibited as well as any traditional architecture pastiche
The fittings or extensions of existing buildings must respect the character of the initial building with regard to the harmony of volumes, the scale of the drilling and the associations of materials and colors.
-
- MATERIALS
Constructions must be made of materials whose shade is as close as possible to the traditional materials used in the region.
A) Facades:
Facade walls that are not made of materials intended to remain apparent, such as cut stone, apparatused rubble, slate essentage, solid grouted brick, slate ensentage, must receive a facing or plaster, either dyed in the mass, or painted.
The plasters or paints must be of a light tone, harmonizing with the tone of the Caen stone. Any painting, or colored element, distinct from the general tone of the construction, must be motivated by the arrangement of the volumes or architectural elements The use of white color on exterior walls is prohibited.
Are prohibited
• the bare use, in facing, of materials manufactured to be covered with a coating or coating, such as plaster tile, hollow brick. However, exposed concrete can be authorized if it is made with apparatus formwork and cast with care in order to remain raw.
• imitations of materials such as faux brick, faux panels of wood.
B) Covers:
Constructions with a simm will be covered with slate or natural or aged flat tile.
Are admitted:
• materials with a similar appearance (slate, stained fiber, etc....)
• the large mold mechanical tile (22 m2) with a flat pure brown tone.
Are prohibited for constructions for residential use
• the square model slate placed diagonally.
• the large mold mechanical tile models with dimensions, diamonds or similar patterns.
• corrugated fiber cement plates,
• unconcealed metallic materials (galvanized sheet metal).
For the annexes to the house, the same building materials must be used as for the main building.
-
- SHAPES AND VOLUMES:
Regardless of the size of the volume of the construction, elongated proportions are recommended.
A) roofs of buildings for residential use
Roofs with symmetrical gables with a slope of 40° to 60° are mandatory. Terraced roofs are prohibited.
However, roofs with a single low slope are allowed for constructions for annex use located in a separate limit.
Geai wings or "Norman croups" are prohibited.
Any roof overhangs will be limited to 15 cm.
The skylights, if they are not included in the roof plan, will be straight and implanted in the lower part of the slope and of vertical and narrow shape.
These provisions do not apply in the case of repair of the roofs of existing buildings.
Different characteristics may be authorized for existing constructions in the case of the extension or connection of the existing roof to the projected extension.
-
- FENCES:
They must consist of hedges or any other clear-track device.
The full part of the fences must not exceed 1 meter in height.
Are prohibited: molded and prefabricated elements on the edge of the tracks or visible from them.
-
- Various
The construction of annexes such as hutches, chicken coops, shelters, etc. made with makeshift resources are prohibited.
Verandas and greenhouses are not subject to the provisions of this article, with the exception of those relating to general aesthetics.
ARTICLE UD12 - PARKING
Parking of vehicles corresponding to the needs of the constructions must be ensured off public roads.
ARTICLE UD13 - PLANTATIONS
Existing plantations will be maintained or replaced by equivalent plantations.
60% of the land area will be treated in planted green space and will include at least 2 tall trees per 300 m2 of land.
Abandoned parking and road areas must be treated in green spaces.
Wooded areas classified under the "to be preserved or created" plan will be protected and subject to the regime of Article L 130.1 et seq., R 130.1 et seq. of the Urban Planning Code.
ARTICLE UD14 - LAND USE COEFFICIENT (C.O.S.)
The Land Use Coefficient (C.O.S.) defined in Article R 123-22 of the Urban Planning Code is set at 0.20.
For subdivisions and housing groups, the COS applicable to each lot must be fixed by the special regulation so that on average the previous standard on the set in question is not exceeded.
The C.O.S. does not apply to the construction of public or general interest equipment.
ARTICLE UD15 - EXCEEDING THE COEFFICIENT OF LAND USE
Exceeding the C.O.S.:
-
- Is authorized when its application to a plot does not allow to build a minimum area of 200 m2 of off-work floor. In this case, overtaking is possible until this floor surface is obtained. It is then accompanied by the payment of the participation provided for in Article L 332.1. of the Urban Planning Code,
- In case of identical reconstruction after a disaster.
UT ZONE
CHARACTER OF THE AREA
This urban area is mainly used to host tourist and leisure activities.
Only the dwellings necessary for the operation of the activities concerned may be authorized, in addition to the facilities related to these activities.
ARTICLE UT1 - TYPES OF OCCUPATION OR LAND USE AUTHORIZED.
-
- Light leisure accommodation (camping camps, caravans, PRL... as well as the constructions necessary for their operation;
-
- Residential constructions made necessary for the proper functioning of the aforementioned equipment (guarding...
-
- Public or general interest facilities;
-
- Excavations and grounding related to infrastructure equipment and public or general interest equipment.
ARTICLE UT2 - PROHIBITED TYPES OF LAND OCCUPATION OR USE
-
- Occupations and uses of land other than those mentioned in Article UT1, in particular:
-
- Constructions for hotel use;
-
- Facilities classified for environmental protection;
-
- Quarries, excavations and soil raisings except those mentioned in Article UT1;
-
- Makeshift shelters, scrap metal deposits, demolition materials, waste and disused vehicles
ARTICLE UT3 - ACCESS AND ROADS.
Accesses and roads must meet the conditions set out in Article 2 of Title 1 of this Regulation relating to public safety and in particular guarantee the access of firefighting vehicles
ARTICLE UT4 - NETWORKS.
Water:
Connection to the drinking water network is mandatory for any new construction or installation requiring a water supply. Constructions that cannot be served by water are not allowed.
Sanitation:
A) Wastewater:
Connection to the sanitation network is mandatory for any new construction.
In the absence of a network, the autonomous sanitation of buildings in accordance with the departmental health regulations is authorized. The facilities will have to be planned to be easily connectable to the public network when it is built.
B) Rainwater:
When the evacuation network exists, the developments made on any land must be such that they guarantee the flow of rainwater into the collection network.
In the absence of a network, the builder will have to carry out at his expense the improvements allowing the free flow of rainwater. In addition, the manufacturer will carry out on its land and at its expense, appropriate and proportionate devices allowing direct evacuation and without stagnation.
ARTICLE UT5 - LAND CHARACTERISTICS.
Emptiness
ARTICLE UT6 - IMPLANTATION OF CONSTRUCTIONS IN RELATION TO THE TRACKS.
A setback of 10 m is required from the public road axes.
Technical works necessary for the operation of public or general services are not subject to the distance and setback rules.
ARTICLE UT7 - IMPLEMENTATION OF CONSTRUCTIONS IN RELATION TO SEPARATIVE LIMITS.
All construction must be installed with a setback at least equal to half of the difference in altitude between any point of the construction and the point of the nearest parcel boundary, with a minimum of 4 meters.
Technical works necessary for the operation of public or general services are not subject to the distance and setback rules.
ARTICLE UT8 - IMPLANTATION OF CONSTRUCTIONS IN RELATION TO EACH OTHER ON THE SAME PROPERTY
Emptiness
ARTICLE UT9 - GROUND CLEARING OF CONSTRUCTIONS.
The ground clearance of the buildings is set at 25%
ARTICLE UT10 - HEIGHT OF CONSTRUCTIONS
The maximum number of building levels is set at 2, including convertible or non-buildable attics, but not including the basement(s).
The upper level of the ground floor may not exceed the highest level of the natural land, on the right-of-way of the building, by more than 0.60 m.
Infrastructure equipment is exempt from the height rule when its technical characteristics so require.
ARTICLE UT11 - EXTERIOR APPEARANCE
Constructions of any kind must not be affected, by their
Exterior appearance, the character or interest of neighboring places, sites,
To natural or urban landscapes.
All traditional architecture foreign to the region is prohibited as well as any traditional architecture pastiche
The fittings or extensions of existing buildings must respect the character of the initial building with regard to the harmony of volumes, the scale of the drilling and the associations of materials and colors.
-
- MATERIALS
Constructions must be made of materials whose shade is as close as possible to the traditional materials used in the region.
A) Facades:
Facade walls that are not made of materials intended to remain apparent, such as cut stone, apparatused rubble, slate essentage, solid grouted brick, slate ensentage, must receive a facing or plaster, either dyed in the mass, or painted. The plasters or paints must be of a light tone, harmonizing with the tone of the Caen stone. Any painting, or colored element, distinct from the general tone of the construction, must be motivated by the arrangement of the volumes or architectural elements. The use of white color on exterior walls is prohibited.
Are prohibited:
• the bare use, in facing, of materials manufactured to be covered with a coating or coating, such as plaster tile, hollow brick. However, exposed concrete can be authorized if it is made with apparatus formwork and cast with care in order to remain raw.
• Imitations of materials such as false brick, false panels of wood.
B) Covers:
Constructions with a simm will be covered with slate or natural or aged flat tile.
Are admitted:
-
- Materials of similar appearance (slate, stained fiber, etc....)
-
- The large mold mechanical tile (22 m2) with a flat brown tone.
Are prohibited:
-
- The square model slate placed diagonally.
- The mechanical tile large mold models with sides, diamonds with similar patterns.
- Corrugated fiber cement plates.
- Unconcealed metal materials (galvanized sheet metal).
For the annexes to the house, the same building materials must be used as for the main building.
- SHAPES AND VOLUMES:
Regardless of the size of the volume of the construction, elongated proportions are recommended.
A) roofs of buildings for residential use
Symetrical 2-sided roofs with a slope of 40° to 60° are mandatory. Terraced roofs are prohibited.
However, roofs with a single low slope are allowed for constructions for annex use located in a separate limit.
Geai wings or "Norman croups" are prohibited.
Any roof overhangs will be limited to 15 cm.
The skylights, if they are not included in the roof plan, will be straight and implanted in the lower part of the slope and of vertical and narrow shape.
These provisions do not apply in the case of repair of existing building covers.
Different characteristics may be authorized for existing constructions, in particular in the case of the extension or connection of the existing roof to the projected extension.
-
- FENCES:
They must consist of hedges or any other clear-track device.
The full part of the fences must not exceed 1 meter in height.
Are prohibited: molded and prefabricated elements on the edge of the tracks or visible from them.
-
- Various
The construction of annexes such as huts, chicken coops, shelters, etc.. made with makeshift means are prohibited.
Verandas and greenhouses are not subject to the provisions of this article, with the exception of those relating to general aesthetics.
ARTICLE UT12 - PARKING
Parking of vehicles corresponding to the needs of the constructions must be provided off public roads.
ARTICLE UT13 - PLANTATIONS
Existing plantations will be maintained or replaced by equivalent plantations.
In the case of an outdoor accommodation operation (camping, PRL...) at least 10% of the area of the land will be planted in a common area. The plots will have to be separated by hedges composed of regional species.
ARTICLE UT14 - LAND USE COEFFICIENT (C.O.S.)
The possibilities of land use result from the application of Articles UT1 to LIT1 3.
ARTICLE UT15 - EXCEEDING THE COEFFICIENT OF LAND OCCUPATION
NOTHING.
TITLE IlI
PROVISIONS APPLICABLE TO NATURAL AREAS
ZONE 1NA
CHARACTER OF THE AREA
This unequipped natural area is intended, given its situation, to be urbanized in the future.
It must be the subject of a study prior to its urbanization, in order to achieve a coherent development and a good integration into the natural and built environment.
However, this urbanization can be carried out in advance, under certain conditions, and provided that it does not compromise the overall development of the area.
ARTICLE 1NA1 - TYPES OF OCCUPATION OR LAND USE AUTHORIZED.
-
- The layout and measured extension of existing buildings and establishments, as well as their annexes;
-
- Identical reconstruction of existing constructions, after a disaster;
-
- The operations of subdivisions or constructions for the main use of housing, including any collective support equipment to the exclusion of any classified establishment, provided that:
(A) these operations relate to an area of at least 5000 m2 in the case of subdivision or housing groups (except in the case of terminal operation in the area) to 1000 m2 in the case of parcel detachment;
B) the petitioner realizes the internal viability and contributes to the expenses of implementing public equipment in accordance with the provisions of Article R 111-14 of the Urban Planning Code
(C) these operations are compatible with a coherent development of the entire area.
-
- Constructions in the context of these operations
-
- Public or general interest facilities;
-
- Excavations and grounding related to infrastructure equipment;
ARTICLE 1NA2 - TYPES OF LAND OCCUPATION OR USE PROHIBITED
All other types of land occupation or use are prohibited
In particular:
-
- Constructions except those mentioned in Article 1 NA1;
- Facilities classified for environmental protection; l
- Quarries, excavations and soil raisings with the exception of those mentioned in Article 1 Na1;
- Deposits of scrap metal, demolition materials, waste and disused vehicles;
-
- Light leisure accommodation (camping, caravannage, PRL);
-
- Caravan parking regardless of the duration;
ARTICLE 1NA3 - ACCESS AND ROADS.
The accesses and roads created must meet the conditions set out in Article 2 of Title 1 of this safety regulation (Article R 111.4. of the Urban Planning Code)
Regardless of the size of the operations, it will be required in non-private space, the possibility of subsequent road connection with any adjoining operations.
ARTICLE 1NA4 - SERVICE BY NETWORKS
Water: connection to the drinking water network is mandatory for any new construction or installation requiring a water supply. Buildings that cannot be served with water are not allowed.
Sanitation:
A/ Wastewater:
Connection to the collective sanitation network is mandatory for any new construction or installation.
In the absence of a network, the autonomous sanitation of buildings in accordance with the departmental health regulations is authorized. The facilities will have to be planned to be easily connectable to the public network when it is built.
B/ Rainwater:
When the evacuation network exists, the developments made on any land must be such that they guarantee the flow of rainwater into the collection network.
In the absence of a network, the builder will have to carry out at his own expense the developments allowing the free flow of rainwater in accordance with the opinions of the municipality's technical advisory services. In addition, the manufacturer will carry out on its land and at its expense, appropriate and proportionate devices allowing direct evacuation and without stagnation.
ARTICLE 1NA5 - LAND CHARACTERISTICS
To be buildable, new plots created by subdivision or division must have an area of more than 1000 m2.
ARTICLE 1NA6 - IMPLANTATION OF CONSTRUCTIONS IN RELATION TO THE TRACKS.
All new construction must be implemented with a minimum retreat of 5 m from the alignment of the tracks.
Different setbacks may be authorized compared to new roads created on the occasion of subdivisions and housing groups or in the event of extension of existing buildings, provided that there is no inconvenience to safety.
Technical works necessary for the operation of public or general services are not subject to the distance and setback rules.
ARTICLE 1NA7 - IMPLEMENTATION OF CONSTRUCTIONS IN RELATION TO SEPARATIVE LIMITS.
All construction must be built with a setback at least equal to half of the difference in altitude between any point of the construction and the point of the nearest parcel boundary, with a minimum of 4 meters.
Different setbacks may be authorized compared to the new separating limits created on the occasion of subdivisions and housing groups or in the event of extension or development of existing buildings, provided that there is no inconvenience to safety.
Technical works necessary for the operation of public or general services are not subject to the distance and setback rules.
ARTICLE 1NA8 - INSTALLATION OF CONSTRUCTIONS IN RELATION TO EACH OTHER ON THE SAME LAND UNIT.
Two non-contiguous constructions located on the same property must be at a distance from each other at least equal to the height at the sewer of the highest of the two constructions, and never less than 4 meters
ARTICLE 1NA9 - GROUNDING OF CONSTRUCTIONS
The land footprint of the buildings must not exceed 35% of the total area of the plot.
ARTICLE 1NA10 - HEIGHT OF CONSTRUCTIONS
The maximum number of building levels is set at 3, including convertible or non-buildable attics, but not including the basement(s).
The upper level of the ground floor may not exceed the highest level of the natural land, on the right-of-way of the building, by more than 0.60 m.
Infrastructure equipment is exempt from the height rule when its technical characteristics so require.
ARTICLE 1NA11 - EXTERNAL APPEARANCE
Constructions of any kind must not harm, by their external appearance, the character or interest of neighboring places, sites, natural or urban landscapes.
All traditional architecture foreign to the region is prohibited as well as any traditional architecture pastiche
The fittings or extensions of existing buildings must respect the character of the initial building with regard to the harmony of volumes, the scale of the drilling and the associations of materials and colors.
- MATERIALS
Constructions must be made of materials whose shade is as close as possible to the traditional materials used in the region.
A) Facades
Facade walls that are not made of materials intended to remain apparent, such as cut stone, apparatused rubble, slate essentage, solid grouted brick, slate ensentage, must receive a facing or plaster, either dyed in the mass, or painted. The plasters or paints must be of a light tone, harmonizing with the tone of the Caen stone. Any painting, or colored element, distinct from the general tone of the construction, must be motivated by the arrangement of the volumes or architectural elements. The use of white color on exterior walls is prohibited.
Are prohibited:
• the bare use, in facing, of materials manufactured to be covered with a coating or coating, such as plaster tile, hollow brick. However, exposed concrete can be authorized if it is made with apparatus formwork and cast with care in order to remain raw.
• Imitations of materials such as false brick, false panels of wood.
B) Blankets
Constructions with a simm will be covered with slate or natural or aged flat tile.
Are admitted:
-
- Materials of similar appearance (slate, stained fiber, etc....)
-
- The large mold mechanical tile (22 m2) with a flat brown tone.
Are prohibited for constructions for residential use
-
- The square model slate placed diagonally.
-
- The mechanical tile large mold models with sides, diamonds or similar patterns.
-
- Corrugated fiber cement plates.
-
- Unconcealed metal materials (galvanized sheet metal).
For the annexes to the house, the same building materials must be used as for the main building.
-
- SHAPES AND VOLUMES:
Regardless of the size of the volume of the construction, elongated proportions are recommended.
A) roofs of buildings for residential use
Roofs with symmetrical gables with a slope of 40° to 60° are mandatory. Terraced roofs are prohibited.
However, roofs with a single low slope are allowed for constructions for annex use located in a separate limit.
Geai wings or "Norman croups" are prohibited,
Any roof overhangs will be limited to 15 cm.
The skylights, if they are not included in the roof plan, will be straight and implanted in the lower part of the slope and of vertical and narrow shape.
-
- FENCES:
They must consist of hedges or any other clear-track device.
The full part of the fences must not exceed 1 meter in height.
Are prohibited: molded and prefabricated elements on the edge of the tracks or visible from them.
-
- Various
The construction of annexes such as hutches, chicken coops, shelters, etc. made with makeshift resources are prohibited.
Verandas and greenhouses are not subject to the provisions of this article, with the exception of those relating to general aesthetics.
ARTICLE 1NA12 - PARKING
Parking of vehicles corresponding to the needs of the constructions must be ensured off public roads.
ARTICLE 1 NA13 - PLANTATIONS
Existing plantations will be maintained or replaced by equivalent plantations.
For subdivisions and housing groups, a common space must be developed with a minimum area obtained equal to 10% (not including roads) of that of the land.
50% of the area of the plots will be treated in planted green spaces and will include at least one tall tree per 300 m2 of land.
Wooded areas classified on the plan to be preserved or created will be protected and subject to the regime of Articles R 130.1 to R 130.15 of the Urban Planning Code.
ARTICLE 1NA14 - LAND USE COEFFICIENT (C.O.S.)
The Land Use Coefficient (C.O.S.) defined in Article R 123.22 of the Code
Of Urbanism is set at 0.30.
For subdivisions and housing groups, the COS applicable to each lot must be fixed by the special regulation so that on average the previous standard on the set in question is not exceeded.
The C.O.S. does not apply to the construction of public or general interest equipment.
ARTICLE 1NA15 - EXCEEDING THE LAND USE COEFFICIENT (C.O.S.).
Emptiness
NB ZONE
CHARACTER OF THE AREA
This partially equipped natural area is intended to maintain its current character, essentially rural, but where agricultural activity is not predominant.
It is intended to receive a diffuse habitat, subject to sufficient equipment, and exclusively in the form of isolated constructions.
ARTICLE NB1 - TYPES OF OCCUPATION OR LAND USE AUTHORIZED
-
- Constructions for individual housing use and their annexes
-
- Facilities classified for the protection of the environment subject to declaration, provided that they do not present a nuisance for the neighborhood
-
- Constructions for business, hotel, restaurant, office, unclassified activity;
-
- Constructions directly related to agricultural activity;
-
- The layout and measured extension of existing buildings
-
- Public or general interest facilities;
-
- Excavations and grounding related to infrastructure equipment.
ARTICLE NB2 - TYPES OF LAND OCCUPATION OR USE PROHIBITED.
All other types of land occupation or use are prohibited, including:
• subdivisions and housing groups;
• facilities classified for environmental protection, except those mentioned in Article NB1;
• quarries, excavations and ground raisings except those mentioned in Article NB1;
• makeshift shelters, scrap metal deposits, demolition materials, waste, disused vehicles;
• light leisure accommodation (camping, caravans, PRL);
• caravan parking regardless of the duration.
ARTICLE NB3 - ACCESS AND ROADS
The accesses and roads created must meet the conditions listed in Article 2 of Title 1 of this Safety Regulation (Article R 111.4. of the Urban Planning Code
ARTICLE NB4 - SERVICE BY THE NETWORKS
Water :
Connection to the drinking water network is mandatory for any new construction or installation requiring a water supply. Constructions that cannot be served by water are not allowed.
Sanitation:
Wastewater:
Connection to the sanitation network is mandatory for any new construction.
In the absence of a network, the autonomous sanitation of buildings in accordance with the departmental health regulations is authorized. The facilities will have to be planned to be easily connectable to the public network when it is built.
Rainwater:
When the evacuation network exists, the improvements made on any land must be such that they guarantee the flow of rainwater into the collection network.
In the absence of a network, the builder will have to carry out at his expense the improvements allowing the free flow of rainwater. In addition, the manufacturer will carry out on its land and at its expense, appropriate and proportionate devices allowing direct evacuation and without stagnation.
ARTICLE NB5 - LAND CHARACTERISTICS
Any land whose area is less than 1,000 m2 is unbuildable, unless it is the development or measured extension of an existing building, or public or general interest equipment.
ARTICLE NB6 - IMPLANTATION OF CONSTRUCTIONS IN RELATION TO THE TRACKS
Any new construction must be implemented with a minimum retreat of 5 meters from the alignment of the tracks.
However, the retreat from the axis of departmental roads is increased to 15 meters.
The latter limit may be lowered when it is an agricultural technical building or a residential annex to be integrated into a pre-existing complex.
In the case of reconstruction of an annex building to an existing house, the alignment of the dwelling may be renewed.
Different retreats may be allowed if the typology of the island or street in question justifies it, provided that it does not cause any inconvenience to safety.
Technical works necessary for the operation of public or general services are not subject to the distance and setback rules.
ARTICLE NB7 - IMPLANTATION OF CONSTRUCTIONS IN RELATION TO SEPARATIVE LIMITS
All construction must be installed with a setback at least equal to the difference in altitude between any point of the construction and the point of the nearest parcel boundary, with a minimum of 4 meters.
However, are authorized, in separating limits
- constructions with a total height of less than 3 meters. This height can be increased to 5 meters at the ridge and 3 meters at the sewer when the wall installed in the separating limit is a gable wall.
- in order to ensure the harmony of the facades, constructions backing on existing buildings of higher heights within the height limits defined in Article NB10
Different setbacks may be allowed in the event of an extension of existing buildings.
Technical works necessary for the operation of public or general services are not subject to the distance and setback rules.
ARTICLE NB8 - IMPLANTATION OF CONSTRUCTIONS IN RELATION TO EACH OTHER ON THE SAME PROPERTY.
Two non-contiguous constructions located on the same property must be at a distance from each other at least equal to the height at the sewer of the highest of the two buildings and never less than 4 meters.
This distance can be halved when the opposite parts of facades do not have main bays. It is specified that kitchen berries are assimilated for the application of this article, to main berries.
ARTICLE NB9 - GROUND CLEARING OF CONSTRUCTIONS
NEANT
ARTICLE NB10 - HEIGHT OF CONSTRUCTIONS
The maximum number of building levels is set at 3, including convertible or non-buildable attics, but not including the basement(s).
The upper level of the ground floor may not exceed the highest level of the natural land, on the right-of-way of the construction, by more than 0.60 m.
Infrastructure equipment is exempt from the height rule when its technical characteristics so require.
ARTICLE NB11 - EXTERIOR APPEARANCE
Constructions of any kind must not harm, by their external appearance, the character or interest of neighboring places, sites, natural or urban landscapes.
All traditional architecture foreign to the region is prohibited as well as any traditional architecture pastiche
The fittings or extensions of existing buildings must respect the character of the initial building with regard to the harmony of volumes, the scale of the drilling and the associations of materials and colors.
-
- MATERIALS
Constructions must be made of materials whose shade is as close as possible to the traditional materials used in the region.
A) Facades:
Facade walls that are not made of materials intended to remain apparent, such as cut stone, apparatused rubble, slate essentage, solid grouted brick, slate ensentage, must receive a facing or plaster, either dyed in the mass, or painted. The plasters or paints must be of a light tone, harmonizing with the tone of the Caen stone. Any painting, or colored element, distinct from the general tone of the construction, must be motivated by the arrangement of the volumes or architectural elements. The use of white color on exterior walls is prohibited.
Are prohibited :
• the bare use, in facing, of materials manufactured to be covered with a coating or coating, such as plaster tile, hollow brick. However, exposed concrete can be authorized if it is made with apparatus formwork and cast with care in order to remain raw.
• Imitations of materials such as false brick, false panels of wood.
B) Blankets
Constructions with a simm will be covered with slate or natural or aged flat tile.
Are admitted:
• materials with a similar appearance (slate, stained fiber, etc....)
• the large mold mechanical tile (22 m2) with a flat pure brown tone.
Are prohibited for constructions for residential use
• the square model slate placed diagonally.
• the large mold mechanical tile models with dimensions, diamonds or similar patterns.
- Corrugated fiber cement plates.
• unconcealed metallic materials (galvanized sheet metal).
For the annexes to the house, the same building materials must be used as for the main building.
- SHAPES AND VOLUMES:
Regardless of the size of the volume of the construction, elongated proportions are recommended.
A) roofs of buildings for residential use
Symetrical 2-sided roofs with a slope of 40° to 60° are mandatory. Terraced roofs are prohibited.
However, roofs with a single low slope are allowed for constructions for annex use located in a separate limit.
Geai wings or "Norman croups" are prohibited.
Any roof overhangs will be limited to 15 cm.
The skylights, if they are not included in the roof plan, will be straight and implanted in the lower part of the slope and of vertical and narrow shape.
These provisions do not apply in the case of repair of the roofs of existing buildings.
Different characteristics may be authorized for existing constructions in the case, in particular, of the extension or connection of the existing roof to the projected extension.
-
- FENCES:
They must consist of hedges or any other clear-track device.
Solid fences meeting the same provisions as facade walls (see "materials") are authorized over a maximum height of 1.80 meters provided that they do not cause any inconvenience to visibility along public roads.
Are prohibited: molded and prefabricated elements on the edge of the tracks or visible from them.
-
- Various
The construction of annexes such as huts, chicken coops, shelters, etc.. made with makeshift means are prohibited.
Verandas and greenhouses are not subject to the provisions of this article, with the exception of those relating to general aesthetics.
ARTICLE NB12 - PARKING
The parking of vehicles corresponding to the needs of the constructions must be ensured off public roads.
ARTICLE NB13 - PLANTATIONS
Existing plantations will be maintained or replaced by equivalent plantations
Wooded areas classified under the plan "to be preserved or created" will be protected and subject to the regime of Articles L 130.1. et seq. of the Urban Planning Code.
ARTICLE NB14 - LAND OCCUPATION COEFFICIENT
The Land Use Coefficient (C.O.S.) defined in Article R 123.22 of the Urban Planning Code is set at 0.10
The COS does not apply in the case of the construction of public buildings or of general interest.
ARTICLE NB15 - EXCEEDING THE LAND USE COEFFICIENT
Exceeding the C.O.S. is allowed:
• in the event of development or change of use of an existing building within the limits of the pre-existing volume. It is accompanied by the payment of the participation provided for in Article L 332.1 of the Urban Planning Code.
• for identical reconstruction after a disaster.
ZONE NC
CHARACTER OF THE AREA
NC zones are natural areas dedicated to the protection of agricultural activity or soil or subsoil wealth.
Constructions, installations or land uses related to this activity are mainly authorized in these areas.
Nevertheless, the construction of annexes, extension, development and change of use of existing buildings may be authorized for non-agricultural use.
This area may exceptionally receive public facilities of general interest that cannot find their place in residential areas.
Two sub-sectors corresponding to the perimeters of protection of the LOUVIERES drilling are established:
• a sub-sector NCfr close protection perimeter
• a sub-sector NCfé remote protection perimeter
In these areas, land use and activities must comply with the requirements issued by declaration "Public Utility of June 24, 1988.
ARTICLE NC1 - TYPES OF LAND USE OR USE AUTHORIZED
• constructions, including those for residential use, directly related and necessary for farms;
• facilities classified for environmental protection related to and necessary for farming and livestock;
• identical reconstruction after a disaster;
Subject to not harming agricultural activity, the following may also be authorized:
• the layout or measured extension of existing buildings, as well as their annexes;
• the change of use of old buildings of traditional architecture within the strict limit of the existing volume and provided that the state of the building and its architectural interest justify it;
• public or general interest facilities which, by their nature or purpose, cannot be built in residential areas;
• searches and self-exalizations related to infrastructure equipment;
• camping on the farm
ARTICLE NC2 - PROHIBITED TYPES OF LAND OCCUPATION OR USE
All other types of land occupation or use are prohibited, including:
• constructions other than those mentioned in Article NC1
• subdivisions of all kinds and housing groups;
In NCfe and NCfr sectors, these methods of land use are subject to compliance with the terms of the prefectural decree of June 24, 1988 and to the implementation of the technical provisions necessary to maintain water quality.
• quarries, excavations and ground raisings other than those mentioned in Article NC1;
• makeshift shelters, scrap metal deposits, demolition materials, waste, disused vehicles
• light leisure accommodation (camping, caravan, PRL)
• caravan parking for a period of more than 3 consecutive months per year or not.
ARTICLE NC3 - ACCESS AND ROADS
Accesses and roads created must meet the conditions set out in Article 2 of Title 1 of this Safety Regulation (Article R 111.4 of the Urban Planning Code).
ARTICLE NC4 - SERVICE BY NETWORKS
Water:
The connection to the drinking water network is mandatory for any construction for residential use. Constructions that cannot be served by water are not allowed.
Sanitation:
A) Wastewater:
The connection to the sanitation network, if any, is mandatory for any new construction for residential use.
In the absence of a network, the autonomous sanitation of buildings in accordance with the departmental health regulations is authorized. The facilities will have to be planned to be easily connectable to the public network when it is built.
B) Rainwater:
When the evacuation network exists, the developments made on any land must be such that they guarantee the flow of rainwater into the collection network.
In the absence of a network, the builder will have to carry out at his expense the improvements allowing the free flow of rainwater. In addition, the manufacturer will carry out on its land and at its expense, appropriate and proportionate devices allowing direct evacuation and without stagnation.
ARTICLE NC5 - LAND CHARACTERISTICS
No minimum size will be defined for land receiving a new construction, other than for residential use.
The minimum area of land intended to be built for residential use must be 1,000 m2.
ARTICLE NC6 - INSTALLATION OF CONSTRUCTIONS IN RELATION TO THE TRACKS
The following minimum setback is required from the track axis
Mentioned below:
• RD 514 25 m
• other routes ................. 15 m
The latter limit may be lowered when it is an agricultural technical building or a residential annex to be integrated into a pre-existing complex.
In the case of reconstruction of an annex building to an existing house, the alignment of the dwelling may be renewed.
Different retreats may be authorized if the type of island or street in question justifies it, provided that it does not cause any inconvenience to safety.
Technical works necessary for the operation of public or general services are not subject to the distance and setback rules.
ARTICLE NC7 - IMPLANTATION OF CONSTRUCTIONS IN RELATION TO SEPARATIVE LIMITS
All constructions must be implemented
• either in a separating limit,
• either with a setback which cannot be less than 4 m.
Different setbacks may be allowed in the event of an extension of existing buildings, provided that they do not affect security. Technical works necessary for the operation of public or general services are not subject to the distance and setback rules.
ARTICLE NC8 - IMPLEMENTATION OF CONSTRUCTIONS IN RELATION TO EACH OTHER ON THE SAME LAND UNIT
Two non-contiguous constructions, located on the same property, must be located at a distance of at least 4 meters from each other.
ARTICLE NC9 - GROUND CLEARING OF BUILDINGS
N E A N T.
ARTICLE NC10 - HEIGHT OF CONSTRUCTIONS
For constructions for use other than residential
The total height is limited to 12 meters.
For residential constructions
The maximum number of levels of the buildings is set at 3 including the convertible or not convertible attics, but not including the basement(s).
The upper level of the ground floor may not exceed the highest level of the natural land, on the right-of-way of the building, by more than 0.60 m.
Infrastructure equipment is exempt from the height rule when their technical characteristics require it.
ARTICLE NC11 - EXTERIOR APPEARANCE
Constructions of any kind must not harm, by their external appearance, the character or interest of neighboring places, sites, natural or urban landscapes.
All traditional architecture foreign to the region is prohibited as well as any traditional architecture pastiche
The fittings or extensions of existing buildings must respect the character of the initial building with regard to the harmony of volumes, the scale of the drilling and the associations of materials and colors.
-
- MATERIALS
Constructions must be made of materials whose shade is as close as possible to the traditional materials used in the region.
A) Facades:
Facade walls that are not made of materials intended to remain apparent, such as cut stone, apparatused rubble, slate essentage, solid grouted brick, slate ensentage, must receive a facing or plaster, either dyed in the mass, or painted. The plasters or paints must be of a light tone, harmonizing with the tone of the Caen stone. Any painting, or colored element, distinct from the general tone of the construction, must be motivated by the arrangement of the volumes or architectural elements. The use of white color on exterior walls is prohibited.
Are prohibited:
• the bare use, in facing, of materials manufactured to be covered with a coating or coating, such as plaster tile, hollow brick. However, exposed concrete can be authorized if it is made with apparatus formwork and cast with care in order to remain raw.
• imitations of materials such as faux brick, faux panels of wood.
(B) Roofing of residential buildings
Constructions with a simm will be covered with slate or natural or aged flat tile.
Are admitted:
• materials with a similar appearance (slate, stained fiber, etc....)
• the large mold mechanical tile (22 m2) with a flat pure brown tone.
Are prohibited for constructions for residential use:
• the square model slate placed diagonally.
• the large mold mechanical tile models with dimensions, diamonds or similar patterns.
• corrugated fiber cement plates.
• unconcealed metallic materials (galvanized sheet metal).
For the annexes to the house, the same building materials must be used as for the main building.
- SHAPES AND VOLUMES:
Regardless of the size of the volume of the construction, elongated proportions are recommended.
A) roofs of buildings for residential use
Symetrical 2-sided roofs with a slope of 40° to 60° are mandatory. Terraced roofs are prohibited.
However, roofs with a single low slope are allowed for constructions for annex use located in a separate limit.
Geai wings or "Norman croups" are prohibited.
Any roof overhangs will be limited to 15 cm.
The skylights, if they are not included in the roof plan, will be straight and implanted in the lower part of the slope and of vertical and narrow shape.
These provisions do not apply in the case of repair of the roofs of existing buildings.
Different characteristics may be authorized for existing constructions in the case of the extension or connection of the existing roof to the projected extension.
-
- FENCES:
They must consist of hedges or any other clear-track device.
The full part of the fences must not exceed 1 meter in height.
Are prohibited: cement poles, molded and prefabricated elements on the edge of the tracks or visible from them.
-
- MISCELLANEOUS:
The construction of annexes such as hutches, chicken coops, shelters, etc. made with makeshift resources are prohibited.
The verandas and greenhouses are not subject to the provisions of this article, with the exception of those relating to general aesthetics.
ARTICLE NC12 - PARKING
The parking of vehicles corresponding to the needs of the constructions must be ensured off public roads.
ARTICLE NC13 - PLANTATIONS
Existing plantations will be maintained or replaced by equivalent plantations.
Wooded areas classified under the plan to be created or preserved are protected and subject to the regime of articles R 130.1 to R 130.15 of the Urban Planning Code.
ARTICLE NC14 - LAND USE COEFFICIENT
Land use opportunities result from the application of Articles NC1 to NC13.
ARTICLE NC15 - EXCEEDING THE LAND USE COEFFICIENT
Not applicable.
ZONE ND
CHARACTER OF THE AREA
It is a natural area of maintenance of the situation.
They include land that must be subject to special protection due to the quality of the landscape.
In principle, all constructions are prohibited.
Buildings intended to accommodate public or general interest facilities may be exceptionally authorized, except in the NDn and NDa sectors.
Appear in the zoning plan:
- An NDa sector intended to ensure the protection of the surroundings of the church and the mansion of Vaumicel.
- An NDn sector identified among the remarkable areas of the coast pursuant to Article L 146.6. of the Urban Planning Code
ARTICLE ND1 - TYPES OF LAND OCCUPATION OR USE AUTHORIZED
In the ND sector
-
- The layout or measured extension of existing buildings, as well as their annexes;
-
- Identical reconstruction of existing constructions, after a disaster;
-
- The change of use of old buildings of traditional architecture within the strict limit of the existing volume and provided that the state of the building and its architectural interest justify it;
-
- Excavations and grounding related to infrastructure equipment;
-
- Public or general interest facilities which, by their nature or destination, cannot be built in residential areas.
In the NDa sector
-
- The layout or measured extension of existing constructions, as well as their annexes;
-
- Identical reconstruction of existing constructions, after a disaster;
-
- The change of use of old buildings of traditional architecture within the strict limit of the existing volume and provided that the state of the building and its architectural interest justify it;
-
- Excavations and grounding related to infrastructure equipment;
-
- Agricultural technical buildings subject to good integration into the site
In NDn sector
Pedestrian paths and movable objects intended for the reception or information of the public, when they are necessary for the management or opening to the public of these spaces or environments.
ARTICLE ND2 - TYPES OF LAND OCCUPATION OR USE PROHIBITED
All other types of land occupation or use are prohibited, including:
• subdivisions and housing groups
• quarries, excavations and ground rises except those mentioned in Article ND1;
• makeshift shelters, scrap metal deposits, demolition materials, waste, disused vehicles;
• light recreational accommodation (camping, caravan, PRL);
• caravan parking regardless of the duration.
ARTICLE ND3 - ACCESS AND ROADS
The accesses and roads created must meet the conditions set out in Article 2 of Title 1 of this safety regulation (Article R 111.4 of the Urban Planning Code).
ARTICLE ND4 - SERVICE BY NETWORKS
Water:
Connection to the drinking water network is mandatory for any new construction or installation requiring a water supply. Constructions that cannot be served by water are not allowed.
Sanitation:
A/ Wastewater:
Connection to the sanitation network is mandatory for any new construction.
In the absence of a network, the autonomous sanitation of buildings in accordance with the departmental health regulations is authorized. The facilities will have to be planned to be easily connectable to the public network when it is built.
B/ Rainwater:
When the evacuation network exists, the improvements made on any land must be such that they guarantee the flow of rainwater into the collection network.
In the absence of a network, the builder will have to carry out at his expense the improvements allowing the free flow of rainwater. In addition, the manufacturer will carry out on its land and at its expense, appropriate and proportionate devices allowing direct evacuation and without stagnation.
ARTICLE ND5 - LAND CHARACTERISTICS
N E A N T.
ARTICLE ND6 - IMPLANTATION OF CONSTRUCTIONS IN RELATION TO THE TRACKS
The minimum setback required from the public road axis is set at:
• RD 514 25 meters
• other tracks 15 meters
Different setbacks may be allowed in the event of development or extension of existing buildings, provided that they do not cause any inconvenience to security.
Technical works necessary for the operation of public or general services are not subject to the distance and setback rules.
ARTICLE ND7 - IMPLANTATION OF CONSTRUCTIONS IN RELATION TO SEPARATIVE LIMITS
All constructions must be located at a distance of at least 4 m from the separating limit.
Different setbacks may be allowed in the case of existing building development.
Technical works necessary for the operation of public or general services are not subject to the distance and setback rules.
ARTICLE ND8 - IMPLANTATION OF CONSTRUCTIONS IN RELATION TO EACH OTHER ON THE SAME LAND UNIT
Two constructions must be located: either in contiguity or at a distance of at least 2 meters.
ARTICLE ND9 - GROUND CLEARING OF CONSTRUCTIONS
N E A N T.
ARTICLE ND10 - HEIGHT OF CONSTRUCTIONS
In the NDa sector, the height of agricultural technical buildings must not exceed 12 meters.
ARTICLE ND 11 - EXTERIOR APPEARANCE
The exterior appearance of buildings and fences must be recognized in perfect harmony with the natural and built environment.
Constructions of any kind must not affect by their external appearance the character or interest of surrounding places, sites, natural landscapes.
All traditional architecture foreign to the Bessin region is prohibited.
Any pastiche of traditional architecture is prohibited.
ARTICLE ND12 - PARKING
The parking of vehicles corresponding to the needs of the constructions must be ensured off public roads.
ARTICLE ND13 - PLANTATIONS
The suppressed plantations will be replaced by equivalent plantations
The wooded areas listed on the plan are classified to be preserved and protected, and are subject to the regime of Articles L 130,1 et seq., R 130.1 et seq. of the Urban Planning Code.
ARTICLE ND14 - LAND USE COEFFICIENT
No Soil Use Coefficient is fixed.
ARTICLE ND15 - EXCEEDING THE LAND USE COEFFICIENT
Not applicable.